Electrical Substation

Construction and Service Life of GIS Substation

GIS is assembled of standard equipment modules (circuit breaker, current transformers, voltage transformers, disconnect and ground switches, interconnecting bus, surge arresters, and connections to the rest of the electric power system) to match the electrical one-line diagram of the substation. A cross-section view of a 242-kV GIS shows above the construction and typical dimensions.

Construction of GIS Substation:

The modules are joined using bolted flanges with an “O” ring seal system for the enclosure and a sliding plug-in contact for the conductor. Internal parts of the GIS are supported by cast epoxy insulators. These support insulators provide a gas barrier between parts of the GIS or are cast with holes in the epoxy to allow gas to pass from one side to the other.

Up to about 170 kV system voltages, all three phases are often in one enclosure. Above 170 kV, the size of the enclosure for “three-phase enclosure,” GIS becomes too large to be practical. So a “single-phase enclosure” design is used. There are no established performance differences between the three-phase enclosure and single-phase enclosure GIS. Some manufacturers use the single-phase enclosure type for all voltage levels.

Enclosures today are mostly cast or welded aluminum, but steel is also used. Steel enclosures are painted inside and outside to prevent rusting. Aluminum enclosures do not need to be painted but may be painted for ease of cleaning and a better appearance. The pressure vessel requirements for GIS enclosures are set by GIS standards (IEEE Std. C37.122-1993; IEC, 1990), with the actual design, manufacture, and test following an established pressure vessel standard of the country of manufacture. Because of the moderate pressures involved, and the classification of GIS as electrical equipment, third-party inspection and code stamping of the GIS enclosures are not required.

Conductors today are mostly aluminum. Copper is sometimes used. It is usual to silver plate surfaces that transfer current. Bolted joints and sliding electrical contacts are used to join conductor sections. There are many designs for the sliding contact element. In general, sliding contacts have many individually sprung copper contact fingers working in parallel. Usually, the contact fingers are silver plated. A contact lubricant is used to ensure that the sliding contact surfaces do not generate particles or wear out over time.

Related: GIS – Gas Insulated Substations

The sliding conductor contacts make assembly of the modules easy and also allow for conductor movement to accommodate the differential thermal expansion of the conductor relative to the enclosure. Sliding contact assemblies are also used in circuit breakers and switches to transfer current from the moving contact to the stationary contacts.

Support insulators are made of a highly filled epoxy resin cast very carefully to prevent the formation of voids and/or cracks during curing. Each GIS manufacturer’s material formulation and insulator shape has been developed to optimize the support insulator in terms of electric field distribution, mechanical strength, resistance to surface electric discharges, and convenience of manufacture and assembly. Post, disc, and cone type support insulators are used. Quality assurance programs for support insulators include a high voltage power frequency withstand test with sensitive partial discharge monitoring. Experience has shown that the electric field stress inside the cast epoxy insulator should be below a certain level to avoid aging of the solid dielectric material.

The electrical stress limit for the cast epoxy support insulator is not a severe design constraint because the dimensions of the GIS are mainly set by the lightning impulse to withstand level and the need for the conductor to have a fairly large diameter to carry to load current of several thousand amperes. The result is space between the conductor and enclosure for support insulators having low electrical stress.

Service Life of GIS Substation:

The service life of GIS using the construction described above has been shown by experience to be more than 30 years. The condition of GIS examined after many years in service does not indicate any approaching limit in service life. Experience also shows no need for periodic internal inspection or maintenance. Inside the enclosure is a dry, inert gas that is itself not subject to aging. There is no exposure to any of the internal materials to sunlight. Even the “O” ring seals are found to be in excellent condition because there is almost always a “double seal” system —it shows one approach. The lack of aging has been found for GIS, whether installed indoors or outdoors.

Related: Circuit Breaker, Current, And Voltage Transformers, Disconnect And Ground Switches For GIS

Source: ‘Electric Power Substations Engineering’ By Philip Bolin (Mitsubishi Electric Power)

Leave a Comment
Social

Recent Posts

Explore The Pros and Cons of Using Electric Heaters

Electric heaters are truly a benefiting electrical device that has the function of converting a…

2 years ago

Explanation of Power Surge for House

Generally, a power surge can follow in any wire in your very new or old…

3 years ago

Current Transformer – Need, Working, Types, and Losses

Current Transformers (CT) are the devices in which the secondary current used for calculation is…

3 years ago

How to Start and Stop MWM TCG 2020 V 16K Gas Engine Generator?

Recently we installed and commissioned 2nos MWM TCG 2020 V 16K Gas Generator in our…

4 years ago

6 Tips to Choose The Right VFD For Your Electrical Application

If you own a manufacturing plant, a factory assembly line, or any other automated space…

4 years ago

Top 10 Best College or University in India For Electrical Engineering

If you are planning to pursue Bachelor's in Electrical Engineering in India then we have…

5 years ago

ABOUT US | TERM & CONDITIONS | PRIVACY POLICY

 

© 2017 - 2022, By An Electrical Engineer